how to assign material name& quantity in preparation BOM while detailing?

By SURESH YADAV on 22 Jul 18:31 1 answer 0 comments

First I assigned material name individually for each model. Then after?

Added images

Square

1 answer

  • Rasesh Palav
    Rasesh Palav about 3 years ago

    You will have to create a parameter called Material for each part in the assembly and then in the repeat region table, the column material should be having the attribute asm.mbr.user defined with the user defined parameter also called Material