WANT TO REDUCE LEAD LINKS IN REST ROUGHING CAM

HI I AM AMIT RECENTLY I START CAM IN POWER MILL I FACE A PROBLEM LEAD LINKS IN REST ROUGHING AND STOCK MODEL FINISHING , I WAST MORE THEN 50 % TIME IN LEAD LINKS, SO PLEASE SUGGEST ME,

Answer
 
Comments 0

4 Answers

please send the tool path
sheet snap shot & ling snap shot.

 
Comments 0

after generating tool path u should go to lead and link then u have to change the short ,long ,default ,it is commonly appeared as short- safe ,long-safe, default-safe, to reduce the time u may change and check as given below details to reduce time for good time..
short- skim ,
long-incremental,
try this method, and also u can reduce the time by editing skim distance and plunge distance..

 
Comments 0